This project consisted of a new 1,000 square foot steel storage building for TriMet in one of their operating rail yards. The scope of work included meeting with stakeholders to determine design criteria required for the building, design management from schematic design, design development, construction documents, permitting with the City of Beaverton, coordination of bid documents, procurement, construction oversight, close coordination with rail yard workers, weekly meetings, submittal review, RFI’s, change order review and approval, schedule monitoring, daily reports, photo documentation, punch list and close-out documentation.
Project | Storage Building |
---|---|
Role | Project Manager |
Value | $172K |
Completion | 2015 |
Location | Oregon |
Size | 1,000 SF |